Work To Begin On New Bridge For Springdale Rd

Published on Thursday, 25 May 2023 at 2:15:39 PM

Main Roads WA has confirmed to the Shire of Ravensthorpe that construction work for the much anticipated new bridge on Springdale Road will start on Tuesday 6 June 2023, the day after the WA Day public holiday.

The work consists of a new concrete bridge over Jerdacuttup River located on Springdale Road, east of Orchid Road.

While Main Roads WA are undertaking this work Springdale Road will remain closed between Orchid Road and Mary’s Road with signed detours in place. See below.

 

Main Roads WA have advised this work is expected to be completed in March 2024.

 

If you have any questions or concerns about the project please contact:

 

 

Caitlyn Harris

COMMUNITY ENGAGEMENT MANAGER

Main Roads Great Southern Region

p: +61 8 9892 0555

w: www.mainroads.wa.gov.au

 

 

The Shire of Ravensthorpe thanks residents for their patience while this work is being carried out and we look forward to residents using the new bridge in 2024.

 

Back to All News